Scheduling Lean Manufacturing Systems an der TU München

Karteikarten und Zusammenfassungen für Scheduling Lean Manufacturing Systems an der TU München

Arrow Arrow

Komplett kostenfrei

studysmarter schule studium
d

4.5 /5

studysmarter schule studium
d

4.8 /5

studysmarter schule studium
d

4.5 /5

studysmarter schule studium
d

4.8 /5

Lerne jetzt mit Karteikarten und Zusammenfassungen für den Kurs Scheduling Lean Manufacturing Systems an der TU München.

Beispielhafte Karteikarten für Scheduling Lean Manufacturing Systems an der TU München auf StudySmarter:

Example for a Heuristic Method?

Beispielhafte Karteikarten für Scheduling Lean Manufacturing Systems an der TU München auf StudySmarter:

Which different models are there considering the machine configurations?

Beispielhafte Karteikarten für Scheduling Lean Manufacturing Systems an der TU München auf StudySmarter:

What are the objectives of the flexible flow line loading (FFLL) algorithm?

Beispielhafte Karteikarten für Scheduling Lean Manufacturing Systems an der TU München auf StudySmarter:

What performance measures are there?

Beispielhafte Karteikarten für Scheduling Lean Manufacturing Systems an der TU München auf StudySmarter:

What are just-in-time oriented approaches?

Beispielhafte Karteikarten für Scheduling Lean Manufacturing Systems an der TU München auf StudySmarter:

What is car sequencing?

Beispielhafte Karteikarten für Scheduling Lean Manufacturing Systems an der TU München auf StudySmarter:

What is mixed-model sequencing and what are its assumptions?

Beispielhafte Karteikarten für Scheduling Lean Manufacturing Systems an der TU München auf StudySmarter:

What are work oriented approaches?

Beispielhafte Karteikarten für Scheduling Lean Manufacturing Systems an der TU München auf StudySmarter:

What are the objectives of the grouping and spacing (GS) heuristic?

Beispielhafte Karteikarten für Scheduling Lean Manufacturing Systems an der TU München auf StudySmarter:

What is done in the second phase of the FFLL?

Beispielhafte Karteikarten für Scheduling Lean Manufacturing Systems an der TU München auf StudySmarter:

What is done in the first phase of the FFLL?

Beispielhafte Karteikarten für Scheduling Lean Manufacturing Systems an der TU München auf StudySmarter:

What are the three phases of the flexible flow line loading (FFLL) algorithm?

Kommilitonen im Kurs Scheduling Lean Manufacturing Systems an der TU München. erstellen und teilen Zusammenfassungen, Karteikarten, Lernpläne und andere Lernmaterialien mit der intelligenten StudySmarter Lernapp. Jetzt mitmachen!

Jetzt mitmachen!

Flashcard Flashcard

Beispielhafte Karteikarten für Scheduling Lean Manufacturing Systems an der TU München auf StudySmarter:

Scheduling Lean Manufacturing Systems

Example for a Heuristic Method?
Dispatching/priority rules

Scheduling Lean Manufacturing Systems

Which different models are there considering the machine configurations?
single machine models
parallel machine models
flow shop models
job shop models
supply chain models

Scheduling Lean Manufacturing Systems

What are the objectives of the flexible flow line loading (FFLL) algorithm?
– maximize throughput (minimize makespan)
– minimize WIP (reduce blocking probabilities)

Scheduling Lean Manufacturing Systems

What performance measures are there?
Throughput (and Makespan)
Due dates:
– Lateness (positive and negative)
– Tardiness (positive/late only)
Costs:
– Setup Costs
– WIP, Inventory Costs
– Finished Goods Inventory Costs
– Transportation Costs

Scheduling Lean Manufacturing Systems

What are just-in-time oriented approaches?
from TPS
– avoid waste
– reduce inventory as much as possible

material supply according to JIT principle

Scheduling Lean Manufacturing Systems

What is car sequencing?
– aim to find a sequence that minimizes number of rule violations
– requires sequencing rules (Ho:No)
– sliding through the sequence and summing up violations of relevant sub-sequences
– violation occurs if a window of size No contains more than Ho cars containing option o

Scheduling Lean Manufacturing Systems

What is mixed-model sequencing and what are its assumptions?
– aim to minimize total work overload based on a detailed schedule
Assumptions:
– closed stations
– velocity of conveyor belt = 1
– operators return with infinite velocity to next workpiece
– work overload is measured by the time or space necessary to complete all work in excess of the respective stations right border
– work overload has no impact on the succeeding station

Scheduling Lean Manufacturing Systems

What are work oriented approaches?
– aim to minimize work overload
– work overload occurs when operations cannot be finished within stations boundaries

Scheduling Lean Manufacturing Systems

What are the objectives of the grouping and spacing (GS) heuristic?
– minimize total setup cost
– minimize total weighted tardiness
– spacing of capacity constrained operations
– keep a regular rate for material consumption

Scheduling Lean Manufacturing Systems

What is done in the second phase of the FFLL?
– determine the order of jobs
– calculate overloads
– calculate cumulative overloads
– select job with the smallest sum of (positive) overloads and add to the sequence
– repeat

Scheduling Lean Manufacturing Systems

What is done in the first phase of the FFLL?
each job is assigned to a machine
workloads are balanced by using the longest processing time (LPT) heuristic:
– assume all jobs are available at the same time
– sort jobs in decreasing order of their processing times
– whenever one of the machines is freed, select jobs with LPT

Scheduling Lean Manufacturing Systems

What are the three phases of the flexible flow line loading (FFLL) algorithm?
1. machine allocation
2. sequencing
3. release timing

Melde dich jetzt kostenfrei an um alle Karteikarten und Zusammenfassungen für Scheduling Lean Manufacturing Systems an der TU München zu sehen

Singup Image Singup Image
Wave

Andere Kurse aus deinem Studiengang

Für deinen Studiengang Management and Technology an der TU München gibt es bereits viele Kurse auf StudySmarter, denen du beitreten kannst. Karteikarten, Zusammenfassungen und vieles mehr warten auf dich.

Zurück zur TU München Übersichtsseite

Business Analytics

Investment and Financial Management

International relations

User Modeling and Recommender Systems

CH2: Consumer Behavior

CH3: Consumer Behavior

CH4: Consumer Behavior

CH5: Consumer Behavior

CH8: Consumer Behavior

CH10: Consumer Behavior

CH11: Consumer Behavior

CH12: Consumer Behavior

Marketing

R Codes

Anorganische

AC Verbindungen_Tutorien

Einsatz und Realisierung von Datenbanken

chemiesoftware

Was ist StudySmarter?

Was ist StudySmarter?

StudySmarter ist eine intelligente Lernapp für Studenten. Mit StudySmarter kannst du dir effizient und spielerisch Karteikarten, Zusammenfassungen, Mind-Maps, Lernpläne und mehr erstellen. Erstelle deine eigenen Karteikarten z.B. für Scheduling Lean Manufacturing Systems an der TU München oder greife auf tausende Lernmaterialien deiner Kommilitonen zu. Egal, ob an deiner Uni oder an anderen Universitäten. Hunderttausende Studierende bereiten sich mit StudySmarter effizient auf ihre Klausuren vor. Erhältlich auf Web, Android & iOS. Komplett kostenfrei. Keine Haken.

Awards

Bestes EdTech Startup in Deutschland

Awards
Awards

European Youth Award in Smart Learning

Awards
Awards

Bestes EdTech Startup in Europa

Awards
Awards

Bestes EdTech Startup in Deutschland

Awards
Awards

European Youth Award in Smart Learning

Awards
Awards

Bestes EdTech Startup in Europa

Awards

So funktioniert's

Top-Image

Individueller Lernplan

StudySmarter erstellt dir einen individuellen Lernplan, abgestimmt auf deinen Lerntyp.

Top-Image

Erstelle Karteikarten

Erstelle dir Karteikarten mit Hilfe der Screenshot-, und Markierfunktion, direkt aus deinen Inhalten.

Top-Image

Erstelle Zusammenfassungen

Markiere die wichtigsten Passagen in deinen Dokumenten und bekomme deine Zusammenfassung.

Top-Image

Lerne alleine oder im Team

StudySmarter findet deine Lerngruppe automatisch. Teile deine Lerninhalte mit Freunden und erhalte Antworten auf deine Fragen.

Top-Image

Statistiken und Feedback

Behalte immer den Überblick über deinen Lernfortschritt. StudySmarter führt dich zur Traumnote.

1

Lernplan

2

Karteikarten

3

Zusammenfassungen

4

Teamwork

5

Feedback