Item     PV          AC          EV

1        10,000    11,000    10,000

2        9,000     8,000     7,000

3        8,000     8,000     8,000

4        7,000      7,000     5,000

Which item is most over budget?

Which item has the lowest SPI?

Lösung anzeigen
TESTE DEIN WISSEN

Item 1

Lösung ausblenden
TESTE DEIN WISSEN

Which process creates an approximate monetary value for each project activity necessary to complete the work of the project?

Lösung anzeigen
TESTE DEIN WISSEN

Plan Cost Management

Lösung ausblenden
TESTE DEIN WISSEN

Which CPI measurement indicates that the project is currently experiencing a cost underrun?

Lösung anzeigen
TESTE DEIN WISSEN

CPI = 1.2

Lösung ausblenden
TESTE DEIN WISSEN

What is a key benefit of the Plan Cost Management process?

Lösung anzeigen
TESTE DEIN WISSEN

Provides estimates for project costs at the beginning of the project

Lösung ausblenden
TESTE DEIN WISSEN

Your project has a dependency on an outside contractor and that contractor has fallen behind schedule. The contractor is promising to make up the ground lost and complete on their original deadline. You have calculated the following values for the current point infime: BAC = $12000, PV = $8000, EV = $7000, AC = $9000, SPI = 0.87, and CPI = 0.77. In order for the contractor to meet the original plan, what level of efficiency must the contractor maintain for the remainder of the project?

Lösung anzeigen
TESTE DEIN WISSEN

60%

Lösung ausblenden
TESTE DEIN WISSEN

In an agile/adaptive environment project that has high variability but must also hold to a strict budget, what approach should the project manager take to stay within the cost constraints?

Lösung anzeigen
TESTE DEIN WISSEN

Adjust the scope and schedule.

Lösung ausblenden
TESTE DEIN WISSEN

In which process is the project manager performing a variane analysis in order to take any necessary corrective actions to realign the project work with the project budget?

Lösung anzeigen
TESTE DEIN WISSEN

Plan Cost Management

Lösung ausblenden
TESTE DEIN WISSEN

What estimation technique is your builder using if the cost has been presented to you as $100 per square foot?

Lösung anzeigen
TESTE DEIN WISSEN

Analogous estimating

Lösung ausblenden
TESTE DEIN WISSEN

Which estimation technique can make use of either triangular distribution or beta distribution?

Lösung anzeigen
TESTE DEIN WISSEN

Analogous estimating

Lösung ausblenden
TESTE DEIN WISSEN

You are calculating costs for your project based on costs from a previous similar project that was completed last month in your organization. This process is known as:

Lösung anzeigen
TESTE DEIN WISSEN

Analogous estimating

Lösung ausblenden
TESTE DEIN WISSEN

Your project sponsor for the current project expects to receive a narrow estimate for project costs because all project information is now known. Which of the following is considered a suitable range for this request?

Lösung anzeigen
TESTE DEIN WISSEN

-100% to +100%

Lösung ausblenden
TESTE DEIN WISSEN

What process are you performing if you are adding together the costs of individual activities into work packages and then rolling the work packages into control accounts and finishing with summarizing the control accounts?

Lösung anzeigen
TESTE DEIN WISSEN

Plan Cost Management

Lösung ausblenden
  • 6539 Karteikarten
  • 433 Studierende
  • 0 Lernmaterialien

Beispielhafte Karteikarten für deinen Cost Kurs an der University of Trento - von Kommilitonen auf StudySmarter erstellt!

Q:

Item     PV          AC          EV

1        10,000    11,000    10,000

2        9,000     8,000     7,000

3        8,000     8,000     8,000

4        7,000      7,000     5,000

Which item is most over budget?

Which item has the lowest SPI?

A:

Item 1

Q:

Which process creates an approximate monetary value for each project activity necessary to complete the work of the project?

A:

Plan Cost Management

Q:

Which CPI measurement indicates that the project is currently experiencing a cost underrun?

A:

CPI = 1.2

Q:

What is a key benefit of the Plan Cost Management process?

A:

Provides estimates for project costs at the beginning of the project

Q:

Your project has a dependency on an outside contractor and that contractor has fallen behind schedule. The contractor is promising to make up the ground lost and complete on their original deadline. You have calculated the following values for the current point infime: BAC = $12000, PV = $8000, EV = $7000, AC = $9000, SPI = 0.87, and CPI = 0.77. In order for the contractor to meet the original plan, what level of efficiency must the contractor maintain for the remainder of the project?

A:

60%

Mehr Karteikarten anzeigen
Q:

In an agile/adaptive environment project that has high variability but must also hold to a strict budget, what approach should the project manager take to stay within the cost constraints?

A:

Adjust the scope and schedule.

Q:

In which process is the project manager performing a variane analysis in order to take any necessary corrective actions to realign the project work with the project budget?

A:

Plan Cost Management

Q:

What estimation technique is your builder using if the cost has been presented to you as $100 per square foot?

A:

Analogous estimating

Q:

Which estimation technique can make use of either triangular distribution or beta distribution?

A:

Analogous estimating

Q:

You are calculating costs for your project based on costs from a previous similar project that was completed last month in your organization. This process is known as:

A:

Analogous estimating

Q:

Your project sponsor for the current project expects to receive a narrow estimate for project costs because all project information is now known. Which of the following is considered a suitable range for this request?

A:

-100% to +100%

Q:

What process are you performing if you are adding together the costs of individual activities into work packages and then rolling the work packages into control accounts and finishing with summarizing the control accounts?

A:

Plan Cost Management

Cost

Erstelle und finde Lernmaterialien auf StudySmarter.

Greife kostenlos auf tausende geteilte Karteikarten, Zusammenfassungen, Altklausuren und mehr zu.

Jetzt loslegen

Das sind die beliebtesten Cost Kurse im gesamten StudySmarter Universum

INTRO TO COST

University of Lagos

Zum Kurs
COST

University of Delhi

Zum Kurs
COSTOS

Universidad Nacional de Misiones

Zum Kurs
COSTOS

Universidad Nacional Autónoma de México

Zum Kurs
Costos I

Universidad de Concepcion

Zum Kurs

Die all-in-one Lernapp für Studierende

Greife auf Millionen geteilter Lernmaterialien der StudySmarter Community zu
Kostenlos anmelden Cost
Erstelle Karteikarten und Zusammenfassungen mit den StudySmarter Tools
Kostenlos loslegen Cost