Study with flashcards and summaries for the course Scheduling Lean Manufacturing Systems at the TU München

Exemplary flashcards for Scheduling Lean Manufacturing Systems at the TU München on StudySmarter:

Example for a Heuristic Method?

Exemplary flashcards for Scheduling Lean Manufacturing Systems at the TU München on StudySmarter:

Which different models are there considering the machine configurations?

Exemplary flashcards for Scheduling Lean Manufacturing Systems at the TU München on StudySmarter:

What are the objectives of the flexible flow line loading (FFLL) algorithm?

Exemplary flashcards for Scheduling Lean Manufacturing Systems at the TU München on StudySmarter:

What performance measures are there?

Exemplary flashcards for Scheduling Lean Manufacturing Systems at the TU München on StudySmarter:

What are just-in-time oriented approaches?

Exemplary flashcards for Scheduling Lean Manufacturing Systems at the TU München on StudySmarter:

What is car sequencing?

Exemplary flashcards for Scheduling Lean Manufacturing Systems at the TU München on StudySmarter:

What is mixed-model sequencing and what are its assumptions?

Exemplary flashcards for Scheduling Lean Manufacturing Systems at the TU München on StudySmarter:

What are work oriented approaches?

Exemplary flashcards for Scheduling Lean Manufacturing Systems at the TU München on StudySmarter:

What are the objectives of the grouping and spacing (GS) heuristic?

Exemplary flashcards for Scheduling Lean Manufacturing Systems at the TU München on StudySmarter:

What is done in the second phase of the FFLL?

Exemplary flashcards for Scheduling Lean Manufacturing Systems at the TU München on StudySmarter:

What is done in the first phase of the FFLL?

Exemplary flashcards for Scheduling Lean Manufacturing Systems at the TU München on StudySmarter:

What are the three phases of the flexible flow line loading (FFLL) algorithm?

Your peers in the course Scheduling Lean Manufacturing Systems at the TU München create and share summaries, flashcards, study plans and other learning materials with the intelligent StudySmarter learning app.

Get started now!

Flashcard Flashcard

Exemplary flashcards for Scheduling Lean Manufacturing Systems at the TU München on StudySmarter:

Scheduling Lean Manufacturing Systems

Example for a Heuristic Method?
Dispatching/priority rules

Scheduling Lean Manufacturing Systems

Which different models are there considering the machine configurations?
single machine models
parallel machine models
flow shop models
job shop models
supply chain models

Scheduling Lean Manufacturing Systems

What are the objectives of the flexible flow line loading (FFLL) algorithm?
– maximize throughput (minimize makespan)
– minimize WIP (reduce blocking probabilities)

Scheduling Lean Manufacturing Systems

What performance measures are there?
Throughput (and Makespan)
Due dates:
– Lateness (positive and negative)
– Tardiness (positive/late only)
Costs:
– Setup Costs
– WIP, Inventory Costs
– Finished Goods Inventory Costs
– Transportation Costs

Scheduling Lean Manufacturing Systems

What are just-in-time oriented approaches?
from TPS
– avoid waste
– reduce inventory as much as possible

material supply according to JIT principle

Scheduling Lean Manufacturing Systems

What is car sequencing?
– aim to find a sequence that minimizes number of rule violations
– requires sequencing rules (Ho:No)
– sliding through the sequence and summing up violations of relevant sub-sequences
– violation occurs if a window of size No contains more than Ho cars containing option o

Scheduling Lean Manufacturing Systems

What is mixed-model sequencing and what are its assumptions?
– aim to minimize total work overload based on a detailed schedule
Assumptions:
– closed stations
– velocity of conveyor belt = 1
– operators return with infinite velocity to next workpiece
– work overload is measured by the time or space necessary to complete all work in excess of the respective stations right border
– work overload has no impact on the succeeding station

Scheduling Lean Manufacturing Systems

What are work oriented approaches?
– aim to minimize work overload
– work overload occurs when operations cannot be finished within stations boundaries

Scheduling Lean Manufacturing Systems

What are the objectives of the grouping and spacing (GS) heuristic?
– minimize total setup cost
– minimize total weighted tardiness
– spacing of capacity constrained operations
– keep a regular rate for material consumption

Scheduling Lean Manufacturing Systems

What is done in the second phase of the FFLL?
– determine the order of jobs
– calculate overloads
– calculate cumulative overloads
– select job with the smallest sum of (positive) overloads and add to the sequence
– repeat

Scheduling Lean Manufacturing Systems

What is done in the first phase of the FFLL?
each job is assigned to a machine
workloads are balanced by using the longest processing time (LPT) heuristic:
– assume all jobs are available at the same time
– sort jobs in decreasing order of their processing times
– whenever one of the machines is freed, select jobs with LPT

Scheduling Lean Manufacturing Systems

What are the three phases of the flexible flow line loading (FFLL) algorithm?
1. machine allocation
2. sequencing
3. release timing

Sign up for free to see all flashcards and summaries for Scheduling Lean Manufacturing Systems at the TU München

Singup Image Singup Image
Wave

Other courses from your degree program

For your degree program Management And Technology at the TU München there are already many courses on StudySmarter, waiting for you to join them. Get access to flashcards, summaries, and much more.

Back to TU München overview page

Business Analytics

Investment and Financial Management

International relations

User Modeling and Recommender Systems

CH2: Consumer Behavior

CH3: Consumer Behavior

CH4: Consumer Behavior

CH5: Consumer Behavior

CH8: Consumer Behavior

CH10: Consumer Behavior

CH11: Consumer Behavior

CH12: Consumer Behavior

Marketing

R Codes

Anorganische

AC Verbindungen_Tutorien

Einsatz und Realisierung von Datenbanken

chemiesoftware

What is StudySmarter?

What is StudySmarter?

StudySmarter is an intelligent learning tool for students. With StudySmarter you can easily and efficiently create flashcards, summaries, mind maps, study plans and more. Create your own flashcards e.g. for Scheduling Lean Manufacturing Systems at the TU München or access thousands of learning materials created by your fellow students. Whether at your own university or at other universities. Hundreds of thousands of students use StudySmarter to efficiently prepare for their exams. Available on the Web, Android & iOS. It’s completely free.

Awards

Best EdTech Startup in Europe

Awards
Awards

EUROPEAN YOUTH AWARD IN SMART LEARNING

Awards
Awards

BEST EDTECH STARTUP IN GERMANY

Awards
Awards

Best EdTech Startup in Europe

Awards
Awards

EUROPEAN YOUTH AWARD IN SMART LEARNING

Awards
Awards

BEST EDTECH STARTUP IN GERMANY

Awards

How it works

Top-Image

Get a learning plan

Prepare for all of your exams in time. StudySmarter creates your individual learning plan, tailored to your study type and preferences.

Top-Image

Create flashcards

Create flashcards within seconds with the help of efficient screenshot and marking features. Maximize your comprehension with our intelligent StudySmarter Trainer.

Top-Image

Create summaries

Highlight the most important passages in your learning materials and StudySmarter will create a summary for you. No additional effort required.

Top-Image

Study alone or in a group

StudySmarter automatically finds you a study group. Share flashcards and summaries with your fellow students and get answers to your questions.

Top-Image

Statistics and feedback

Always keep track of your study progress. StudySmarter shows you exactly what you have achieved and what you need to review to achieve your dream grades.

1

Learning Plan

2

Flashcards

3

Summaries

4

Teamwork

5

Feedback